Gallant Avenue storm sewer replacement

Map showing the location of the storm sewer being replaced

To help reduce the risks of flooding, we replaced the storm sewer along Gallant Avenue in Deep Cove.

The existing storm sewer — which was subject to flooding in 2014 and 2018 — was replaced due to the increasingly heavy storms caused by our changing climate. The new sewer will be able to handle a one-in-200-year flood, help mitigate debris flows (branches, mud, and rocks that can block sewers), and provide improved habitat for fish in the inlet.

News and updates

May 2022 – Storm sewer project complete 

The Gallant Avenue storm sewer replacement project is now finished, and the construction detour has been closed. In April 2022, Council approved the revegetation of Naughton Avenue and the installation of an unpaved walking pathway between Deep Cove Road and Deep Cove Crescent.

Thank you for your patience as we completed this important infrastructure project.

April 27, 2022 – Final paving on Gallant Avenue and Naughton detour closure

Final paving on Gallant Avenue is scheduled for Thursday, April 28, weather permitting. On paving day, a full road closure of upper Gallant will be required. Please follow all detour signage and traffic control instructions.

Following road markings and line painting on Friday, April 29, the Naughton Avenue construction detour will be closed to vehicles.

April 19, 2022 – Preparation for final paving on Gallant Avenue  

Final paving on Gallant Avenue is scheduled for late April, weather permitting. The Naughton Avenue construction detour will be temporarily reopened on April 19 for approximately two weeks to allow crews to prepare for this work.

A full closure of upper Gallant Ave with a traffic detour will be required for two days to complete the final paving.

February 4, 2022 – Two-way traffic set to return on Gallant Avenue

The Naughton Avenue detour is scheduled to close towards the end of next week, following the substantial completion of the sidewalks on Gallant Avenue. Full-time, two-way traffic is expected along Gallant until the Naughton detour is temporarily reopened in the spring for the final sidewalk work and paving on Gallant Avenue.

Please note that parking along Gallant may be restricted to allow the contractors to do landscaping and other work.

We look forward to completing the landscaping work in Panorama Park in early spring and welcoming the public to enjoy the park once it is complete.

January 21, 2022 – Construction update

Sidewalk construction on Gallant Avenue is nearing completion. Once the sidewalks are constructed, two-way traffic will return on Gallant Avenue, and the Naughton Avenue detour will be closed. The detour will be briefly reopened later in the spring to allow for the final paving of Gallant.

Our contractor is also preparing to start landscaping in Panorama Park, with plans for completion by mid-spring. We appreciate the patience from the community and all park users as we work to reopen the entire area as soon as possible.

January 7, 2022 – Construction work set to resume

Weather-dependent construction work is scheduled to start the week of January 10. Much of the remaining work is landscaping, which will require slightly warmer temperatures.

Before the holiday break, sidewalks were poured on the south side of Gallant Avenue. The remaining section of the sidewalks and plaza will be constructed once weather conditions are suitable. The detour will close once single-lane alternating traffic is no longer required for the project. Final paving will take place in the spring.

With the recent snowfall and rain, please use caution as the ground may be slippery and uneven in some spots, especially areas that have not yet been paved. As always, please walk within the designated areas and follow the instruction of traffic control workers.

December 17, 2021 – Gallant Avenue holiday work schedule update

Construction crews will be pausing work for the holidays from December 24 to January 3. Access to businesses will remain open at all times, with temporary walkways in place where necessary.

The Naughton Avenue detour will remain open over the holidays, as some work remains on Gallant Avenue to be completed in 2022. 

With snow in the forecast, our crews are prepped and ready to respond. Please exercise caution as winter conditions can cause slippery roads and sidewalks, especially as temperatures dip below freezing.

We wish you all a happy holiday and look forward to completing this important community flood protection project with minimal disruptions in 2022.

December 10, 2021 – Gallant Ave base-layer paving complete; detour remains in place

The base layer of asphalt and curbs have been laid down on upper Gallant Avenue, and temporary road markings are in place. The Naughton Avenue detour will remain open to one-way traffic while work requiring lane closures on Gallant Avenue is completed.

Traffic exiting Deep Cove will be routed along Gallant Ave. Please follow directions from traffic flaggers, and obey all traffic signs in the area.

Due to the unprecedented flooding, subsequent highway closures and supply chain disruptions in the Fraser Valley, our contractor will continue working on the sidewalks and other construction activities into the new year. Access to businesses will remain open at all times.

Please note the Naughton Avenue detour survey closes December 12. We encourage you to share your feedback on what you think should happen in the area.

December 3, 2021 – Gallant Avenue reopen 

[3:45pm] Gallant Avenue has reopened to outbound traffic following bottom lift paving and line-painting. This is an important milestone for the Gallant Avenue storm sewer replacement project and we thank you for your patience.

December 2, 2021 – Closure of upper Gallant and traffic detour in Deep Cove 

This Friday, December 3, due to anticipated favourable weather conditions, we are proceeding with paving work on upper Gallant Avenue. This will require a one-day full road closure of upper Gallant Avenue, between 7am and 8pm.

As a result of this paving work and road closure, vehicle traffic will be routed out of Deep Cove Village via the following detour: Naughton Avenue, Rockcliff Road, Raeburn Street, Banbury Road, Cliffmont Road to Deep Cove Road. Please see map below. Traffic flaggers will be posted at key intersections along the detour route to control traffic, assist buses and vehicles, and maintain safety for pedestrians and cyclists exiting the neighbourhood. 

Access to Caledonia Avenue north of Gallant Avenue will be maintained via single-lane alternating traffic on Deep Cove Road.

Expect traffic delays throughout Deep Cove on Friday between 7am and 8pm. Please follow directions from traffic flaggers and leave yourself extra time to get to your destination.

We acknowledge the late notice for this closure and detour. Dry weather conditions are critical to paving work, and so we need to take advantage of the few remaining good weather days when forecasted in order to complete this important work.

Thank you for your understanding and patience as we work to complete the construction works on upper Gallant Avenue.

A map of the traffic detour on upper Gallant.

November 30, 2021 – Naughton detour reopening temporarily

The detour on Naughton Avenue will be temporarily reopened to ensure safe and efficient access in and out of Deep Cove during the heavy rain forecast this week.

Since the detour closed, more single-lane alternating traffic has been required than was initially anticipated, and significant rainfall from heavy storms in quick succession has created potholes on the gravel surface on upper Gallant.

Contractors will begin reopening the detour on Tuesday, November 30.

November 26, 2021 – Naughton Avenue detour closed

As significant construction nears completion, the Naughton Avenue detour was closed earlier this week. Traffic has been routed back onto Deep Cove Road and Gallant Avenue, and most remaining work on upper Gallant can be completed with a return to two-way traffic. Single-lane alternating traffic will be necessary intermittently over the next few weeks but is expected to become progressively less frequent towards construction completion. This is a standard practice for road construction that we apply across the District.

The temporary detour was constructed to avoid long wait times in the summer months due to heavy traffic. Now that traffic has returned to lower, off-season volumes, anticipated delays are expected to be minimal so in keeping with our previous commitment to the community, we closed the temporary construction detour. A couple of unforeseen challenges occurred mid-week due to weather impacts, resulting in more single-lane alternating traffic than we anticipated. We have been working to address these challenges and starting next week, anticipate less single lane alternating traffic which should bring traffic delays closer to wait times associated with other construction projects in our community.

This weekend, heavy rainfall is expected to continue and crews will be out managing creek and surface flows. Generators and pumps potentially needed for this mitigation work may be audible in the worksite area.

Please use extra caution when walking and driving in the area. 

November 18, 2021 – Upcoming closure of Naughton Avenue detour 

With the installation of the culvert now complete, the Naughton Avenue detour is expected to close during the week of November 22.  

After the detour is closed, two-way traffic will resume on upper Gallant Avenue during non-construction hours. During construction hours, single-lane alternating traffic will be required to accommodate completion of road construction on upper Gallant.

Crews expect to pour new curbs on Gallant Avenue early in the week. Sidewalk construction, paving, and landscaping will follow over the next several weeks.

Naughton Avenue feedback survey

Starting Monday, November 22, we are seeking community feedback on possible directions for the future of the Naughton Avenue area. This engagement is to provide information to Council for direction on next steps. Learn more.

October 29 – Gallant construction work update

Construction work will be ongoing along Gallant Avenue and in the creek. Crews continue to replace sidewalks on Gallant Avenue and prepare for planting new trees. Where possible, the contractor will perform weekend work from 7am-7pm Saturdays and Sundays. On October 31, any heavy work will stop at 5pm. 

Please exercise caution around the construction site, especially on Halloween. Follow the directions of the traffic control flaggers and project personnel. Temporary walkways will remain installed, and access to businesses will remain open at all times. 

October 22, 2021 – Construction work on Gallant

Construction work will be ongoing this weekend on Gallant Avenue between Panorama Drive and Caledonia Avenue, as well as in Panorama Park. Weekend working hours are between 7am-7pm. Temporary walkways will remain installed, and access to businesses will remain open at all times. Please follow the directions of traffic control flaggers and project personnel.

Last week, the contractor hit a major milestone in completing the concrete culvert pipe, and the culvert was operational for last weekend’s heavy rains. Inlet and outlet channel work is continuing as weather permits.

October 15, 2021 – Preparing for heavy rain

Heavy rain is forecast to begin on Friday, October 15 and continue through the weekend. Crews will be on-site to monitor and control water flows in Gallant Creek.

During the week of October 18, crews will begin removing sidewalks along both sides of Gallant Avenue between Panorama Drive and Caledonia Avenue. Temporary walkways will be installed, and access to businesses along Gallant Avenue will remain open at all times. Please follow the directions of traffic control flaggers and project crews.

Weather permitting, creek channel work along Gallant Avenue and Panorama Park will be ongoing, and weekend work may be necessary starting October 23.

September 27, 2021

On Thursday, September 20, contractor crews will be observing the National Day for Truth and Reconciliation. Only workers needed to maintain the creek bypass are expected on site.

Please note, due to continued heavy rainfalls expected this week, crews may need to work outside of regular working hours to ensure safe passage of creek flows.

September 16, 2021 – Preparation for heavy rains

Heavy rains are forecast to begin on Friday, September 17, and continue overnight into Saturday, September 18. We are taking additional measures and contingency plans are in place to control water flows in Gallant Creek, including adding extra water pumps.

Crews will be working in the area over the weekend. Residents and businesses may notice noise from water pumps and additional lighting. Please use added caution when travelling on Gallant Ave., Panorama Dr., and Deep Cove Rd. and obey flaggers as traffic patterns may change at short notice.

September 14, 2021 – Update on the storm sewer replacement project

Project manager Wendelin Jordan provides the latest update on the Gallant Avenue storm sewer replacement project.

 

September 3, 2021 – Culvert construction continues up Gallant Ave., businesses remain open

During the week of September 6-10, storm culvert installation will progress from the intersection of Gallant Ave. and Panorama Dr. and head up Gallant Ave.

To accommodate this work, construction fencing on upper Gallant is expected to be moved mid-week to the sidewalk next to the businesses on the north side of Gallant, and pedestrian patios on this section of the street will be removed.

All businesses will remain open and be accessible to pedestrians. During construction work on upper Gallant, the street will remain open to one-way traffic and two-way pedestrian traffic; however, some sidewalk closures will be necessary.

August 27, 2021

During the week of August 30, construction will be moving into the intersection at Gallant Avenue and Panorama Drive. Two additional street trees on upper Gallant must be removed in order to facilitate the construction of the storm culvert.

In addition, the street lights on Gallant Avenue will be decommissioned and replaced with temporary street lighting for the duration of the project. The permanent street lights will be reinstated at the end of the project. 

August 20, 2021 – Culvert construction work

During the week of August 23-27, new culvert and creek outlet construction continues in Panorama Park. Pipe installation crews will be working towards the intersection of Gallant Ave and Panorama Drive and later heading west up Gallant Ave. Expect minor traffic delays.

August 13, 2021 – Culvert construction work 

During the week of August 16-20, construction continues on the new culvert and creek outlet in Panorama Park. Storm culvert installation will likely extend into the intersection of Gallant Ave and Panorama Dr by mid-week. This work will involve the use of large equipment, so expect minor traffic delays.

August 6, 2021 – Culvert and creek outlet construction work

During the week of August 9-13, construction continues on the new culvert and creek outlet in Panorama Park. We expect the delivery of a large excavator on Monday, August 9, that will require short road closures on Deep Cove Road and Gallant Avenue.

July 30, 2021 – New culvert construction 

Starting the week of August 3, construction will begin on the new culvert outlet in Panorama Park, behind the Deep Cove Cultural Centre. This work will include anchor drilling, excavation, and deliveries of materials. On Wednesday, August 4, we are also anticipating the delivery of a large crane, which will require two 5-10 minute full road closures on Deep Cove Road and Gallant Avenue from Naughton Avenue to Panorama Drive.

July 29, 2021 – Water main works and ties completed

The water main works and tie-ins have been successfully completed. 

July 26-28, 2021 — Water main work and overnight water shutoffs 

The contractor installing new water mains on Gallant Avenue and Panorama Drive will be completing building water service connections from July 26 to July 28. As a result, water services will be shut off from 9:00pm to 6:00am during the nights of July 26 and July 27 to complete work in the affected areas. Impacted businesses and residents will be notified by the contractor with further details.

June 28, 2021 — Naughton detour opens July 5

The opening of the Naughton Avenue detour is planned for July 5. Crews will be completing temporary line painting and landscaping along the detour throughout the week of June 28. The July 5 opening will coordinate with TransLink rerouting schedules for buses.

Please expect single-lane alternating traffic on Panorama Drive north of Gallant Avenue continuing from Monday through Wednesday as crews work to relocate the sanitary sewer.

June 21, 2021 — Sanitary sewer relocation

Excavation work begins to relocate a sanitary sewer in Panorama Park. There will be intermittent single-lane alternating traffic on Panorama Drive for the next 1-2 weeks.

June 20, 2021 — BC Hydro work on upper Gallant

BC Hydro crews will be working on upper Gallant starting at 8am on Sunday, June 20. The south side of the sidewalk will be closed. Please use caution and expect intermittent traffic delays. This BC Hydro repair work is not related to the Gallant storm sewer project.

June 14-18, 2021 — Single-lane alternating traffic

During the week of June 14-18, there will be single-lane alternating traffic on parts of Deep Cove Road connecting to Gallant Avenue and a temporary pedestrian walkway in the area. Please use caution and expect traffic delays.

May 17, 2021 — Start of contract works

Conwest is beginning onsite preparations for the project, including creating a site office and equipment and materials storage area in the Panorama Park upper parking lot. As a result, there will be changing traffic flow patterns and increased activity in the area. Please observe instructions given by traffic control personnel and follow COVID protocols when approaching site personnel.

Throughout the week, construction activities will increase, and crews are expected to start breaking ground on Tuesday, May 25, 2021. Please observe all parking restrictions and other signage on-site to ensure your safety and workers’ safety.

May 16, 2021 — BC Hydro scheduled power outage 

BC Hydro has informed us that on Sunday, May 16, there will be a power outage due to required electrical works in the area. BC Hydro will contact affected customers directly regarding the duration and timing of outages.

May 2021 — Construction start

Conwest Contracting has been selected to construct the Gallant Storm Sewer Replacement Project. Conwest will begin preliminary works throughout May, including construction on the temporary detour on Naughton Avenue. 

April 12, 2021 — BC Hydro infrastructure relocations update

Pre-works for the BC Hydro infrastructure relocation are complete. There will be a pause in work until BC Hydro crews complete the final tie-ins, which is expected to happen in the next several weeks and will last only a few days.

There will be some single-lane alternating traffic and a short, scheduled power outage. More details on the dates and the scheduled power outage will be posted here once confirmed.

March 25, 2021 — BC Hydro infrastructure relocations have started

Crews are now working on upper Gallant Avenue and Deep Cove Road to relocate BC Hydro’s electrical infrastructure. These relocations must be completed before any other work can begin on this project.

The current BC Hydro work will take approximately 3-4 weeks. During this period, you may experience some travel delays; please allow for additional time in your travel schedule.

March 17, 2021 — Share your ideas for Naughton Avenue

To accommodate construction, we are creating a temporary detour using Naughton Avenue. We want to know what you think should be done once construction is complete.

Should Naughton Avenue become a multi-use path? Be removed and retreed? Kept as a vehicle link? Used a different way? Nothing is off the table, so please share your ideas!

Tell us your ideas for Naughton Ave

Detour and traffic impacts

Current traffic impacts

December 10, 2021 – The base layer of asphalt and curbs have been laid down on upper Gallant Avenue, and temporary road markings are in place. The Naughton Avenue detour will remain open to one-way traffic while work requiring lane closures on Gallant Avenue is completed.

Traffic exiting Deep Cove will be routed along Gallant Ave. Please follow directions from traffic flaggers, and obey all traffic signs in the area.

December 2, 2021: This Friday, December 3, due to anticipated favourable weather conditions, we are proceeding with paving work on upper Gallant Avenue. This will require a one-day full road closure of upper Gallant Avenue, between 7am and 8pm.

As a result of this paving work and road closure, vehicle traffic will be routed out of Deep Cove Village via the following detour: Naughton Avenue, Rockcliff Road, Raeburn Street, Banbury Road, Cliffmont Road to Deep Cove Road. Please see map below. Traffic flaggers will be posted at key intersections along the detour route to control traffic, assist buses and vehicles, and maintain safety for pedestrians and cyclists exiting the neighbourhood. 

Access to Caledonia Avenue north of Gallant Avenue will be maintained via single-lane alternating traffic on Deep Cove Road.

Expect traffic delays throughout Deep Cove on Friday between 7am and 8pm. Please leave yourself extra time to get to your destination.

We acknowledge the late notice for this closure and detour. Dry weather conditions are critical to paving work, and so we need to take advantage of the few remaining good weather days when forecasted in order to complete this important work.

Thank you for your understanding and patience as we work to complete the construction works on upper Gallant Avenue.

A map of the traffic detour on upper Gallant.

September 16, 2021: Heavy rains are forecast to begin on Friday, September 17, and continue overnight into Saturday, September 18. We are taking additional measures and contingency plans are in place to control water flows in Gallant Creek, including adding extra water pumps. Crews will be working in the area over the weekend. Please use added caution when travelling on Gallant Ave., Panorama Dr., and Deep Cove Rd. and obey flaggers as traffic patterns may change at short notice.

August 23-27, 2021: New culvert and creek outlet construction continues in Panorama Park. Pipe installation crews will be working towards the intersection of Gallant Ave and Panorama Drive and later heading west up Gallant Ave. Expect minor traffic delays.

August 16-20, 2021: Storm culvert installation will likely extend into the intersection of Gallant Ave and Panorama Dr by mid-week. This work will involve the use of large equipment, so expect minor traffic delays.

August 9, 2021: There will be short road closures (5-10 minutes) on Deep Cove Road and Gallant Avenue to accommodate the delivery of a large excavator required for construction.

August 4, 2021: There will be two 5-10 minute road closures on Wednesday, August 4 on Deep Cove Road and Gallant Avenue from Naughton Avenue to Panorama Drive to accommodate the delivery of a large crane required for construction. 

June 28, 2021: The opening of the Naughton Avenue detour is planned for July 5. Crews will be completing temporary line painting and landscaping along the detour throughout the week of June 28. The July 5 opening will coordinate with TransLink rerouting schedules for buses. Please expect single-lane alternating traffic on Panorama Drive north of Gallant Avenue continuing from Monday through Wednesday as crews work to relocate the sanitary sewer.

June 21, 2021: Excavation work begins to relocate a sanitary sewer in Panorama Park. There will be intermittent single-lane alternating traffic on Panorama Drive for the next 1-2 weeks.

June 20, 2021: BC Hydro crews will be working on upper Gallant starting at 8am on Sunday, June 20. The south side of the sidewalk will be closed. Please use caution and expect intermittent traffic delays.

June 14-18, 2021: There will be single-lane alternating traffic on parts of Deep Cove Road connecting to Gallant Avenue and a temporary pedestrian walkway in the area. Please use caution and expect traffic delays.

Effective May 2, 2021: Expect intermittent, short duration weekday lane closures for utility work on Gallant Ave near Caledonia Ave.

View our map of District-wide construction-related traffic impacts

Detours during construction

Replacing the storm sewer requires significant excavation of upper Gallant Avenue, which will disrupt traffic and parking in the area. 

To ensure the safe and efficient flow of cars, bikes, and pedestrians in and out of Deep Cove, we will create a detour by temporarily opening and extending approximately 100 metres of the Naughton Avenue right-of-way between Panorama Drive and Deep Cove Road. 

This will allow us to create a short, counter-clockwise one-way loop, as shown here.

Map of construction detour route around Gallant Ave

Details & Drawings

Updated engineering drawings

 The following are updated drawings for the Naughton Avenue detour, the Panorama Park landscaping and the upper Gallant north sidewalk. Other drawings can be obtained by sending a request to JordanW@dnv.org. Please note that the Naughton Avenue detour drawing is subject to change based on community feedback about traffic operations on Naughton east of Deep Cove Crescent.

Take a closer look at the sewer replacement project

Watch this video for complete details of the Gallant Avenue storm sewer replacement project, including information about the temporary construction detour and our plans for traffic management and pedestrian safety during construction. 

The video is a rerecording of a staff presentation to the Deep Cove Community Association on January 27, 2021.

Get an update on the sewer replacement project

Watch this video for updates on our revegetation plans, the Naughton detour design, our upcoming public engagement process regarding the final use of the detour, and more. The information in this video builds on information shared during the January 27, 2021 video.

The video is a rerecording of a staff presentation to the Deep Cove Community Association on March 17, 2021.

Background

Creating the detour route

A temporary detour using Naughton Avenue is the safest and most effective way to minimize disruption to Deep Cove residents and businesses throughout construction. By temporarily opening Naughton Avenue, we can:

  • avoid single lane alternating traffic through the work zone, which would result in heavy delays exiting Deep Cove during the busy summer season
  • avoid a circuitous detour through the surrounding neighbourhood and elementary school
  • improve the safety and performance of the Panorama/Gallant intersection by streamlining traffic
  • ensure emergency response vehicles have direct access into and out of Deep Cove

Other routes we considered

Other construction detour options were evaluated to preserve the safe and efficient flow of pedestrians, transit, and traffic into, out of, and within Deep Cove during the storm sewer project including:

  1. Single lane alternating traffic on upper Gallant
  2. Clockwise or counter-clockwise one-way loop along Cliffmont, past Cliffmont Elementary and along Rockcliff
  3. One-way loop into and out of Deep Cove on a new Naughton Avenue extension, connecting Deep Cove Road to Naughton Avenue (the chosen option)

We assessed each option for pedestrian and cyclist safety, traffic flow and delay, and traffic and transit operation. Vehicle, cyclist, and pedestrian counts were taken at several locations throughout Deep Cove and used to simulate mobility and delay. We also evaluated impacts to transit service and assessed each route for operational issues such as road widths and turning radius.

The single lane alternating option on Gallant was eliminated because it would cause gridlock exiting Deep Cove for residents, transit, and visitors.

The Cliffmont/Rockcliff route was eliminated because of pedestrian safety close to the elementary school, excessive delays along the entire route, road width and turning radii challenges for vehicles, and extensive impacts to transit service and routing.

The Naughton Avenue extension has minimal impact to traffic flow, is the safest option for pedestrians, has very minimal impact on transit service, and has sufficient width to accommodate traffic safely.

Learn about other ways we're improving Deep Cove

Other projects

Other projects in Deep Cove

The provincial and federal governments are offering grant funding to communities who want to improve their outdoor spaces, in light of the COVID-19 pandemic. We are exploring opportunities to create a more livable Deep Cove by applying for this funding, which would cover 100% of the costs involved.

For more information on this project, please visit the Livable Deep Cove page.

This proposal is not directly related to the Gallant Ave storm sewer replacement project. The temporary construction detour being put in place to accommodate the sewer replacement does not need to remain in place at the end of the project in order for this project to work. 

As this video overview explains, this project is subject to approval of the grant funding and public engagement with the community.

Get project updates delivered to your inbox

Submit your name and email address, and we'll keep you updated about progress with this project.  

Reaching our climate action and environmental health goals

We're taking action in six key areas to reduce greenhouse gas emissions, protect and enhance ecosystem health and biodiversity, and improve our resilience to climate change.

Was this page helpful?

Thanks for your input.