Montroyal Bridge


We are replacing Montroyal Bridge over Mosquito Creek. It is over 60 years old, and has limited capacity.

The bridge and adjoining roadway form part of a major thoroughfare through the District’s Upper Capilano and Delbrook neighbourhoods, connecting Capilano Road to Lonsdale Avenue. This route is heavily used by area commuters, transit, and cyclists.

Construction begins the week of April 10, 2017, and be completed in the summer of 2018.

Traffic impacts

Upcoming work that will impact traffic and access

Week of October 9, 2017 — Single lane alternating traffic

We are currently demolishing the old bridge. During this work, single lane alternating traffic will be required between 9am and 3pm.

General traffic management and access

Single lane alternating traffic

Single lane alternating traffic at the bridge will be implemented on an as-needed basis. 

When single lane traffic is necessary, it will be limited to weekdays between 7am and 8pm. Flaggers will be on site to assist traffic, but expect possible delays.

Trail access during construction

The trail along Mosquito Creek in the vicinity of the construction site is closed for the duration of the project, as are the stairs leading down to the trail from the bridge. Signs showing the trail area that is closed are posted along the trail.

Please use the Sunnycrest Drive trailhead (700m south of the construction area) to detour around the construction, rather than cutting through the private properties adjacent to the bridge.

How we're managing traffic during construction

We are installing a temporary detour bridge just north of the existing bridge. This bridge — which will have a sidewalk and room for two lanes of traffic — will significantly minimize traffic delays and congestion.

We will still need to close Montroyal Blvd to traffic over several weekends during construction, but will provide advance notice of these closure dates once they have been confirmed.

News and updates

October 13, 2017 — Demolition underway

With the new, temporary detour bridge now in place, crews have begun demolishing the old bridge. This is the last step before construction of the new bridge begins.

September 8, 2017 — Temporary bridge opened

The temporary bridge installed next to the existing bridge is now open in both directions. This allows us to begin demolishing the old bridge in the coming weeks.

July 6, 2017 — Temporary bridge installation

Work began on the installation of a temporary bridge next to the existing bridge. This temporary bridge will allow us to maintain traffic flow and access for emergency vehicles while the new, permanent bridge is being constructed.

March 30, 2017 — Construction to begin week of April 10

The contract for construction has now been awarded, and work crews will begin mobilizing on site the week of April 10. Once construction begins, we will keep the "Traffic impacts" tab updated with real-time information about potential lane closures and other delays, or watch for updates on Twitter (#montroyal). 

January 24, 2017 — Bids for construction now being accepted

We are accepting bids for construction until the end of January, 2017. After we evaluate the bids, we will award the contract, and construction can begin. The first step in construction will be to create the detour directly north of the existing bridge.

November 14, 2016 — Detailed design work now complete

We spent the summer working with consultants and utility providers, and consulting local residents, to complete the detailed design for both the bridge, and the road approaching the bridge. The design is now complete (view a render of the final design in the 'Renderings and photos' tab).

We will begin accepting construction bids from seven pre-qualified general contractors in December, 2016.

May 10, 2016 — Construction work delayed until late 2016

Construction has been delayed until late 2016. The bridge was originally planned to be ‘design build,’ which means that one team would carry out both the design and construction. Now, the detailed design will be completed by an independent design team, and then put out to tender sometime in the fall for construction.

There are many challenging aspects to this project, and the delay will allow the design team more time to develop the best value solutions to the District.

The delay also helps avoid compounding traffic disruptions from other construction projects scheduled this summer, including the paving of Capilano Road, development projects in Edgemont Village area, and works on West Queens Road.

February 22, 2016 — Work begins on the new bridge

Early site preparation for the new bridge started this week, with the removal of trees along the north and south sides of Montroyal Blvd. This was necessary to allow for a wider road, and to accommodate the installation of a temporary detour bridge just north of the existing bridge.

Renderings and photos

Construction photos

Select any image to view a larger size, or to scroll through all the images.

Bridge rendering

Final design of the bridge, October 2016.

Rendering of new bridge on Montroyal

Details

Estimated construction schedule

We anticipate construction to begin in spring 2017, and be completed in about one year. Here is a general construction schedule, which we will update as more information becomes available.

  • December, 2016 — Begin accepting construction bids from seven pre-qualified general contractors
  • January, 2017 — Deadline to receive bid submissions from contractors
  • Spring, 2017 — Begin construction, starting with the detour directly north of the existing bridge
  • TBA — Open the new bridge and remove the detour, and complete finishing works (such as landscaping)

Features of the new bridge

Once completed, the new, wider bridge will provide better options for walking, cycling, and safe driving. It will include:

  • two lanes of traffic
  • sidewalks and bike lanes on both sides
  • a new sidewalk on the north side of Montroyal Blvd (from the bridge west to Palisade Drive)
  • new street lighting

Background

How this project was prioritized

The District’s Asset Management Plan (AMP) for Bridges profiles the Montroyal Bridge Replacement Project as one of our top infrastructure replacement priorities. The project was fast tracked after the AMP was completed due to results from the bridge’s re-inspection and capacity assessment.